Operational Standards Rules
The Explanatory Notes to the Draft Building Safety Bill, were initially published by the Ministry of Housing, Communities & Local Government on 20 July 2020, and suggested that Operational Standards Rules are ‘Rules for local authorities and building control bodies setting out the performance requirements to be met in the exercise of their building control functions.’
The final relevant provisions for operational standards rules (OSRs) are set out in sections 58Z – 58Z10 of the Building Act 1984. The regulatory authority may revise the OSRs and publish those revisions at any time. The guidance 'operational standards rules' (OSRs) is also available from the UK government via the link.
OSRs apply to building control functions delivered by local authorities and registered building control approvers. The OSRs adopt the definitions within the act, including:
- building control functions in section 58Z (3)
- duty holder in schedule 1
- initial notice in section 47
- local authority in section 126
- regulatory authority in section 58A
- registered building control approver (RBCA) in section 58N
- registered building inspector (RBI) in section 58B
- restricted activities and functions in section 46A
Local authorities and RBCAs must comply with the OSRs. The regulatory authority may take action against those who fail to fulfil the requirements of the OSRs. The guidance 'operational standards rules' (OSRs) sets the detail of these, within four categories which are as follows:
- Systems and controls
- Persons involved in the delivery of building control functions
- Building control functions
- Enforcement and intervention
[edit] Related articles on Designing Buildings
Featured articles and news
Tackle the decline in Welsh electrical apprenticeships
ECA calls on political parties 100 days to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.